Despite another mixed week of weather we have managed to take advantage of a dry day on Tuesday to install the concrete slab to Block 1. The floor construction starts with the pre-cast concrete beam & block floor and is then covered with a gas resistant membrane and thick insulation. A concrete screed is then installed using a pump to the area of the floor.