Monday, 2 September 2013

Internal works are now ongoing in both blocks. Block 1 has been 1st fixed by all trades and the final plasterboard & plaster skim are ongoing as shown in the photograph. The internal cabling is fixed in a service cupboard on each floor and brought to ground level where it can be installed to the incoming electric service. Block 2 stonework will be completed this week allowing render works to commence.