The installation of the roof covering is ongoing on Block 1 and the soffits/fascia have been fitted. The reconstituted stone walling in now underway with the photograph showing the installed cavity tray. Block 2 is under construction with the timber frame wall panels & floor cassettes being fitted.
 
 


 
 